Project Description

The works involve the hydraulic restructuring, isolation of zones, tertiary network reinforcement, and rehabilitation of tertiary network in As Salt.

(Water Primary Distribution Pipeline DN200, Approx. length 0.35 KM; Water Tertiary Network PE63 & PE125, appox. Length 52.2KM; House Connections, appox. 2,900)

Project Info

Client:Water Authority of Jordan
Year Completed:Nov-2014 to June- 2016